Eli Drilling will continue placing Bluebird underground fiber optic lines on Ohio Street, south of Crawford on the west side down to Belmont.

Work will be in grass areas with minimal sidewalk closures. No road closures are expected at this time.

The fiber optic cabling and related facilities will connect existing cell towers and future 5G cell towers providing exceptional cell service and high speed networks.

Work in this area will continue until October 22nd, 2021.

Questions can be directed to Bluebird contact David Frazier at 816-237-2125 or Eli Drilling contacts, Richard Huston 830-312-0731 or Josh Gruver 830-328-1236.